| |
The Secacao Hydroelectric Project is a 15.6 MW new hydroelectric
development constructed by a private Guatemalan corporation in rural
northeastern Guatemala. The project is located on Rio Trece Aguas,
about 80 km from the city of Coban. Design conditions are approximately
760 meters of head at a flow of 3.6 cubic meters per second. Water is
conveyed from an intake structure via a 42-inch diameter steel penstock
approximately 2,500 meters to a powerhouse containing a single two-jet
horizontal pelton turbine and a synchronous generator rated at 19,300
kVA. A 65-km transmission line at 69 kV was constructed to deliver the
project output to the utility grid. The developers sell all project
output to the state utility, INDE, under the terms of a long-term power
purchase agreement.
EES Consulting personnel were originally retained to assist in
evaluating turbine and generator bids for the project. Based on the
large number of alternatives proposed by equipment vendors, EESC staff
worked with the client to refine the project design criteria and to
develop specifications to provide the vendors with a common basis for
bidding. The scope then expanded to include overall project design
review, bid document and contract terms and conditions development,
contract negotiation, shop drawing reviews and overall construction
management and start-up assistance.
EES Consulting staff worked with the owner’s engineers to develop a
detailed plant operating philosophy to guide both the equipment
selection and the overall plant final design. Detailed specifications
for the controls system, penstock design and installation, spare parts,
operation and maintenance procedures and plant commissioning, start-up
and testing procedures were prepared. A complete water-to-wire
equipment bid package was developed, including contractual terms and
conditions (also developed by EES Consulting staff). The package was
rebid and staff performed a detailed bid analysis and award
recommendation. EES Consulting staff then participated in detailed
negotiations with the apparent low bidder in the USA, Guatemala, and
Austria and helped to develop a conformed contract, which was executed
on December 20, 1996. EES Consulting staff performed several equipment
inspections at the factory during fabrication. Delivery of all
equipment was completed in February 1998. A variety of construction
management tasks were performed including shop drawing reviews,
equipment inspections and insuring conformance with the contract and
the specifications. Jack Snyder of EES Consulting spent 3 months at the
jobsite providing installation inspection on all equipment and controls
and acting as startup coordinator. The Project has operated very
successfully since start-up in 1998.
EES Consulting has recently been retained to perform preliminary design
of a small re-regulating reservoir to be constructed just upstream of
the project dam to allow the project to maximize on-peak energy
production.
|
|